Projected and constructed from 2005-2006.
The building P+1, with three exhibition halls,
each 3.500 m2, on the first floor and the conference
hall, technique and technologic rooms at the ground floor; total
surface 21.000 m2.
The whole one side length 250m, the pavilion is laying along the
existing pavilion No 2 that is connected to with common vestibule.
The reflexive glass in the combination with alucobond makes
structural, ventilated facade. The building was contacted "key turn"
and the projecting and the construction, including all the
engineering installations were finished in only 15 months.
Among the existing supports of
the podium of the complex
"Ekspocenter" there were adopted the new ones for the accepting of
the loading of the roof construction. The limit in the carry
of the fundament that
requested the appliance of lighter
roof construction. That is why there was necessary to install the
"VS" construction that was developed by the president of the firm in
the end of 80'.…